Wind farm costs

This section contains information about wind farm costs (both as lifetime costs and a detailed cost breakdown) and about levelised cost of energy (LCOE).

Costs

Site definitions

We have calculated a set of costs for a floating offshore wind farm, based on the following site conditions and assumptions:

Guide categoriesRounded costUnit
Year of FID2028
First operation date2030
Wind farm rating1000MW
Turbine rating15MW
Water depth at site100m
Annual mean wind speed at 100 m height10m/s
Distance from offshore substation to shore75km
Distance from shore to onshore substation10km
Distance from wind farm to construction port75km
Distance from wind farm to O&M port75km
Floating substructure material and typeSteel semi-submersible
Mooring system6 point mooring with drag embedment anchors
Floating substructure manufacturing locationAsia
Floating substructure assembly locationEurope
Offshore substation foundation typeFixed jacket foundation
Ground conditionsBenign, allowing a piled substructure for the substation and drag embedment anchors for the floating offshore wind turbines
パラメーターデータ単位
最終投資決定 (FID) の年2028
最初の稼働日2030
風力発電所の定格出力1000MW
タービン定格15MW
サイトの水深100m
高度100m での年間平均風速10m/s
洋上変電所から海岸までの距離75km
海岸から陸上変電所までの距離10km
風力発電所から建設港までの距離75km
風力発電所から O&M ポートまでの距離75km
浮体式基礎構造物の材質と種類鋼製セミサブ型
係留施設ドラッグ式埋め込みアンカーによる 6 点係留
浮体式基礎構造物の製造拠点アジア
浮体式基礎構造物の組み立て場所欧州
洋上変電所基礎の種類着床式ジャケット基礎
地盤条件好適であり、変電所のパイル基礎構造物が使用可能であり、浮体式洋上風力タービンについてはドラッグ式埋め込みアンカーを使用可能
매개변수데이터단위
FID 연도2028
최초 운영일2030
풍력발전단지 등급1000MW
터빈 등급15MW
부지 수심100m
100m 높이 연간 평균 풍속10m/s
해상 변전소부터 해안까지의 거리75km
해안에서 육상 변전소까지의 거리10km
풍력발전단지에서 건설 항구까지의 거리75km
풍력발전단지에서 O&M 항구까지의 거리75km
부유식 하부 구조믈 자재 및 유형강철 반잠수식
계류 장치매립식 드래그 앵커를 사용한 6점 계류 방식
부유식 하부 구조물 제조 위치아시아
부유식 하부 구조물 조립 위치유럽
해상 변전소 기초 구조물 유형고정식 재킷 기초 구조물
지면 조건변전소의 파일형 하부 구조물 및 부유식 해상 풍력 터빈용 매립식 드래그 앵커가 가능할 만큼 양호해야 함

Lifetime costs

The pie chart below shows the contribution of each major cost element to the total lifetime cost of a floating offshore wind farm based on the site conditions and assumptions in the above table.

Detailed cost breakdown

A more detailed breakdown of typical costs is presented in the table below.

  • All costs are real 2025 prices.
  • Figures presented are rounded, hence totals may not equate to the sum of the sub-terms.
  • There can be a range in prices of any element between projects, due to specific timing, local issues, exchange rates, competition and contracting conditions, so values stated should only be seen as indicative.
  • Prices for large components include delivery to nearest port, and supplier and warranty costs.
  • Developer costs (including internal project and construction management, insurance, typically spent contingency and overheads) are included in the highest-level boxes but are not itemised.
CategoryRounded costUnit
Development and project management202,000$/MW
Development and consenting services94,000$/MW
Environmental impact assessments14,000$/MW
Development activities and other consenting services80,000$/MW
Environmental surveys11,000$/MW
Animal surveys (benthic, fish, shellfish, mammals and birds)10,000$/MW
Onshore environmental surveys2,000$/MW
Human impact studies1,000$/MW
Resource and metocean assessment9,000$/MW
Structure5,000$/MW
Sensors4,000$/MW
Maintenance1,000$/MW
Geological and hydrographical surveys12,000$/MW
Geophysical surveys3,000$/MW
Geotechnical surveys6,000$/MW
Hydrographic surveys2,000$/MW
Engineering and consultancy12,000$/MW
Project management63,000$/MW
Wind turbine1,755,000$/MW
Nacelle1,084,000$/MW
Rotor468,000$/MW
Tower202,000$/MW
Balance of plant3,143,000$/MW
Dynamic array cable149,000$/MW
Export cable350,000$/MW
Cable accessories104,000$/MW
Interface39,000$/MW
Cable protection5,000$/MW
Buoyancy3,000$/MW
Connectors and joints56,000$/MW
Floating substructure1,706,000$/MW
Structure1,434,000$/MW
Secondary steel68,000$/MW
Systems119,000$/MW
Corrosion protection85,000$/MW
Mooring systems411,000$/MW
Anchor systems45,000$/MW
Mooring lines and chains227,000$/MW
Jewellery128,000$/MW
Topside connection7,000$/MW
Installation aids4,000$/MW
Offshore substation366,000$/MW
HVAC electrical system104,000$/MW
Auxiliary systems17,000$/MW
Topside structure160,000$/MW
Foundation85,000$/MW
Onshore substation57,000$/MW
Electrical system40,000$/MW
Buildings, access and security17,000$/MW
Installation and commissioning1,789,000$/MW
Inbound transport200,000$/MW
Mooring and anchoring pre-installation199,000$/MW
Floating substructure - turbine assembly93,000$/MW
Crane and lifting equipment44,000$/MW
Technician services14,000$/MW
Marshalling port28,000$/MW
Other6,000$/MW
Floating substructure - turbine installation148,000$/MW
Offshore cable installation223,000$/MW
Onshore export cable installation11,000$/MW
Offshore substation installation68,000$/MW
Onshore substation construction38,000$/MW
Offshore logistics17,000$/MW
Sea-based support8,000$/MW
Marine coordination3,000$/MW
Weather forecasting and metocean data1,000$/MW
Marine safety and rescue6,000$/MW
Contingency and insurance793,000$/MW
Operation, maintenance and service127,000$/MW/Year
Operations, maintenance and service port1,000$/MW/Year
Operations44,000$/MW/Year
Operations control centre2,000$/MW/Year
Training3,000$/MW/Year
Onshore logistics2,000$/MW/Year
Technical resource (onshore and off)9,000$/MW/Year
Admin and support staff (onshore)10,000$/MW/Year
Insurance18,000$/MW/Year
Offshore logistics9,000$/MW/Year
Maintenance and service74,000$/MW/Year
Turbine maintenance and service53,000$/MW/Year
Balance of plant maintenance and service19,000$/MW/Year
Statutory inspections1,000$/MW/Year
Decommissioning584,000$/MW
Floating hull - turbine decommissioning193,000$/MW
Mooring and anchoring decommissioning159,000$/MW
Cable decommissioning178,000$/MW
Substation decommissioning54,000$/MW
ガイドのカテゴリー四捨五入後のコスト単位
開発とプロジェクトの管理202,000$/MW
開発および承認サービス94,000$/MW
環境影響評価14,000$MW
開発活動およびその他の承認サービス80,000$/MW
環境調査11,000$/MW
洋上生物種および生息地調査10,000$/MW
陸上環境調査2,000$/MW
人間活動影響調査1,000$/MW
風資源と気象海象評価9,000$/MW
構造物5,000$/MW
センサー4,000$/MW
メンテナンス1,000$/MW
地質・水文調査12,000$/MW
物理探査3,000$/MW
地質調査6,000$/MW
水文調査2,000$/MW
エンジニアリングとコンサルティング12,000$/MW
プロジェクト管理63,000$/MW
風力タービン1,755,000$/MW
ナセル1,084,000$/MW
ローター468,000$/MW
タワー202,000$/MW
周辺設備3,143,000$/MW
アレイ ケーブル149,000$/MW
エクスポートケーブル350,000$/MW
ケーブル付属品104,000$/MW
インターフェース (接続)39,000$/MW
ケーブル保護5,000$/MW
浮力3,000$/MW
コネクタとジョイント56,000$/MW
浮体式基礎構造物1,706,000$/MW
一次鋼構造物1,434,000$/MW
二次鋼構造物68,000$/MW
基礎構造物補助システム119,000$/MW
腐食保護85,000$/MW
係留施設411,000$/MW
アンカー45,000$/MW
係留索227,000$/MW
接続ジョイント128,000$/MW
上部接続部7,000$/MW
設置補助4,000$/MW
洋上変電所366,000$/MW
高圧交流 (HVAC) 電気システム104,000$/MW
補助システム17,000$/MW
上部構造物160,000$/MW
基礎構造物85,000$/MW
陸上変電所57,000$/MW
電気システム40,000$/MW
建物、アクセス、警備体制17,000$/MW
設置と試運転1,789,000$/MW
搬入輸送200,000$/MW
アンカーと係留策の事前設置199,000$/MW
浮体式基礎構造物 - タービンアセンブリ93,000$/MW
重量物吊り上げ・移動設備44,000$/MW
技術者サービス14,000$/MW
マーシャリング港湾28,000$/MW
その他 設置6,000$/MW
浮体式基礎構造物 - タービン設置148,000$/MW
洋上ケーブル敷設223,000$/MW
陸上エクスポートケーブルの敷設11,000$/MW
洋上変電所の設置68,000$/MW
陸上変電所の建設38,000$/MW
洋上物流17,000$/MW
海上支援8,000$/MW
マリンコーディネーション3,000$/MW
天気予報と気象海象データ1,000$/MW
海上安全と救助6,000$/MW
不測の事態への予備費と保険793,000$/MW
運用、保守管理、サービス127,000$/MW/年
運用、保守、サービス港湾1,000$/MW/年
オペレーション44,000$/MW/年
運用管理センター2,000$/MW/年
トレーニング3,000$/MW/年
陸上ロジスティクス2,000$/MW/年
技術リソース (陸上および洋上)9,000$/MW/年
管理者およびサポートスタッフ (陸上)10,000$/MW/年
保険18,000$/MW/年
洋上アクセス船とロジスティクス9,000$/MW/年
メンテナンスとサービス74,000$/MW/年
タービン保守管理・サービス53,000$/MW/年
周辺設備のメンテナンスおよびサービス19,000$/MW/年
法定検査1,000$/MW/年
廃止584,000$/MW
浮体式基礎構造物 - タービンの廃止193,000$/MW
係留およびアンカーの廃止159,000$/MW
ケーブルの廃止178,000$/MW
変電所の廃止54,000$/MW
가이드 범주반올림한 비용단위
개발 및 프로젝트 관리202,000$/MW
개발 및 인허가 서비스94,000$/MW
환경영향평가(EIA)14,000$/MW
개발 활동 및 기타 인허가 서비스80,000$/MW
환경 조사11,000$/MW
동물 조사(저서생물, 어류, 조개류, 포유류, 조류)10,000$/MW
육상 환경 조사2,000$/MW
인체 영향 연구1,000$/MW
자원 및 해양기상 환경 평가9,000$/MW
구조물5,000$/MW
센서4,000$/MW
유지보수1,000$/MW
지질 및 수로 조사12,000$/MW
물리탐사3,000$/MW
지질탐사6,000$/MW
수로 측량2,000$/MW
엔지니어링 및 컨설팅12,000$/MW
프로젝트 관리63,000$/MW
풍력 터빈1,755,000$/MW
나셀1,084,000$/MW
로터468,000$/MW
타워202,000$/MW
발전보조기기3,143,000$/MW
동적 내부망149,000$/MW
외부망350,000$/MW
케이블 부속품104,000$/MW
인터페이스39,000$/MW
케이블 보호재5,000$/MW
부력체3,000$/MW
커넥터 및 접합 장치56,000$/MW
부유식 하부 구조물1,706,000$/MW
구조물1,434,000$/MW
보조 강철 구조물68,000$/MW
시스템119,000$/MW
부식 방지85,000$/MW
계류 장치411,000$/MW
앵커 시스템45,000$/MW
계류삭과 체인227,000$/MW
부속품(Jewellery)128,000$/MW
상부 연결장치7,000$/MW
설치 보조 도구4,000$/MW
해상 변전소366,000$/MW
HVAC 전기 시스템104,000$/MW
보조 설비17,000$/MW
상부 구조물160,000$/MW
기초 구조물85,000$/MW
육상 변전소57,000$/MW
전기 시스템40,000$/MW
건물, 접근 시설, 보안17,000$/MW
설치 및 시운전1,789,000$/MW
인바운드 운송200,000$/MW
계류 및 앵커링 사전 설치199,000$/MW
부유식 하부 구조물 - 터빈 조립93,000$/MW
크레인 및 인양 장비44,000$/MW
엔지니어 제공14,000$/MW
집하 항구28,000$/MW
기타6,000$/MW
부유식 하부 구조물 - 터빈 설치148,000$/MW
해상 케이블 설치223,000$/MW
육상 외부망 설치11,000$/MW
해상 변전소 설치68,000$/MW
육상 변전소 건설38,000$/MW
해상 물류17,000$/MW
해상 지원8,000$/MW
해양 조정 활동3,000$/MW
일기 예보 및 해상기상 데이터1,000$/MW
해양 안전 및 구조 활동6,000$/MW
비상 상황 및 보험793,000$/MW
작동, 유지보수, 정비127,000$/MW/년
작동, 유지보수, 정비 항만1,000$/MW/년
운영44,000$/MW/년
운영 제어 센터2,000$/MW/년
교육3,000$/MW/년
육상 물류2,000$/MW/년
기술 리소스(육상 및 해상)9,000$/MW/년
관리 및 지원 인력(육상)10,000$/MW/년
보험18,000$/MW/년
해상 물류9,000$/MW/년
유지보수 및 정비74,000$/MW/년
터빈 유지보수 및 정비53,000$/MW/년
발전보조기기 유지보수 및 정비19,000$/MW/년
법정 검사1,000$/MW/년
해체584,000$/MW
부유식 선체 - 터빈 해체193,000$/MW
계류 및 앵커링 해체159,000$/MW
케이블 해체178,000$/MW
변전소 해체54,000$/MW

Levelised cost of energy

Purpose of LCOE

LCOE is defined as the revenue required (from whatever source) to earn a rate of return on investment equal to the discount rate (also referred to as the weighted average cost of capital (WACC) over the life of the wind farm. Tax and inflation are not modelled. In other words, it is the lifetime average cost for the energy produced.

LCOE is used to evaluate and compare the cost of electricity production from different technologies and at different locations. It is a good way to compare the cost of a unit of energy (say in dollars per megawatt hour of electricity ($/MWh)) produced. LCOE does not consider costs relating to balancing supply and demand.

Lower LCOE benefits the electricity consumer (and tax payers if any subsidy is paid to generators), so decreasing LCOE is a key focus for the offshore wind industry.

LCOE combines costs and energy production into one metric, rather than comparing cost and energy production separately. It is used by technology players and industry enablers, but typically not by project investors who may be more interested in internal rate of return (IRR) or net present value (NPV) of an investment, taking into account more company-specific features like tax.

In the UK, subsidy for offshore wind farms is currently provided through UK Government Contract for Difference (CfD) auctions. CfD bid price is the revenue ($/MWh) sought by the developer for a 15 year duration. Revenue after this will come from the open market. The bidder’s prediction of future market prices and its approach to risk and competition will determine how it sets its CfD bid price. The CfD bid price therefore is not equal to LCOE, though there is a relationship between the two. In different markets, the scope of supply of the project developer and the terms of the competition vary, meaning that there is a different relationship between CfD bid price and LCOE.

In Japan, subsidies for offshore wind farms are provided through Public Auction System for Offshore Renewable Energy, established under the Renewable Energy Sea Area Utilization Act (2019). Auctions are conducted by the Ministry of Economy, Trade and Industry (METI) and the Ministry of Land, Infrastructure, Transport and Tourism (MLIT). Developers bid by proposing a supply price (¥/kWh) for a fixed contract period, typically 20 years. After this period, revenue will be determined by market conditions. The bid price is influenced by the developer’s expectations of future electricity prices, risk management strategy, and competitive positioning. Therefore, the bid price is not necessarily equal to the levelised cost of electricity (LCOE), though there is a correlation between the two. The relationship between bid price and LCOE varies depending on market structure, project scope, and auction rules in different regions.

In South Korea, offshore wind subsidies are provided through the Renewable Portfolio Standard (RPS) and the Feed-in-Premium (FIP) scheme, managed by the Ministry of Trade, Industry, and Energy (MOTIE). Unlike competitive auctions in other markets, South Korea’s RPS requires large utilities to source a set percentage of electricity from renewables. Developers earn revenue through Renewable Energy Certificates (RECs) and electricity sales, with offshore wind projects benefiting from higher REC multipliers. Introduced in 2022, the FIP scheme offers a premium above the wholesale market price instead of a fixed tariff, allowing for market-driven pricing. Bid prices reflect forecasts of electricity prices, risk strategies, and competition rather than directly equating to the levelised cost of electricity (LCOE), though a correlation exists. South Korea is transitioning toward competitive bidding for offshore wind, with a roadmap outlining a two-stage evaluation process that considers both price and non-price factors. This shift may reshape the current RPS and FIP frameworks, impacting project economics and investment dynamics.

Definition of LCOE

The technical definition of LCOE is:

Where:

It Investment expenditure in year t
Mt Operation, maintenance and service expenditure in year t
Et Energy generation in years t
r Discount rate (or WACC), and
n Lifetime of the project in years.

Drivers of LCOE

LCOE reduction can come from reduced costs, increased energy production, or changes in financing and lifetime of the project. Reduced cost can result from process or technology changes during the manufacturing, installation or operations phase. Increased energy production may result from technology or by reducing lost energy via better operational processes. Reducing project risk is the main way to affect financing cost.

The chart below shows BVGA’s LCOE forecast for floating offshore wind from 2027 (when the next pre-commercial floating offshore wind farms in the UK are expected to be commissioned) to 2035. LCOE varies between individual projects but overall LCOE is continuing to reduce significantly over time. The band shows the variance in LCOE that could occur for floating offshore wind projects driven by different site conditions, support mechanisms and local requirements that all impact LCOE. The variance is expected to tighten over time as the industry standardises across different technologies, and their associated manufacturing, installation and maintenance processes. The cost breakdown shown below reflects the higher commodity prices and altered market dynamics experienced by the industry post-2020. While some level of reduction in future commodity prices is expected, it is unclear on the timing or magnitude of this.

Some of the key drivers of cost are:

Site conditions

In waters less than 70 m deep, the mooring of some floating substructure types becomes more expensive because of the dynamic response to waves in these shallower waters.

Easy ground conditions, such as dense sand with low gradients or homogeneous or stiff clay containing few or no boulders, offer cost benefits because a range of anchoring solutions can be used and there is high confidence of long-term mooring system stability. Difficult conditions can add to cost significantly by driving a need for alternative designs and installation methods, such as suction or piled anchors.

Wind and wave conditions, tidal ranges and tidal flows also impact LCOE. Higher mean wind speeds increase cost but have a net benefit for LCOE due to increased energy production. In Japan and South Korea, typhoon winds could drive design changes that add cost. Large tidal ranges can add to cost because turbines are required to keep a minimum clearance from sea level to blade tip at all times and so require more flexibility in the mooring system. Tides and waves make it harder to access turbines, especially for unplanned maintenance and repair activities in bad weather, adding cost and reducing energy production.

Likewise, projects further from shore take longer to access which adds cost and increases downtime, which reduces energy production. At about 60 km, it may be most cost effective to use a service operation vessel (SOV) spending weeks at sea, rather than crew transfer vessels (CTVs) travelling to and from port daily. Projects further from shore typically also have longer grid connections, adding to transmission CAPEX and OPEX.

Over time, there has been a move by governments from providing an agreed fixed-value market mechanism to supporting offshore wind to auctions where project developers bid a price for electricity they will generate. This change drives competition at project level which is passed down through the supply chain. Also, as the industry matures, what used to be highly differentiated areas of supply become commodities, driving further competition.

In some supply chain areas, such as turbine supply, the market is not big enough to have more than a handful of suppliers competing globally. This limits competition. In other areas, such as cables and foundations, transport costs are low enough to enable a geographically diverse supply base to bid for supply. In locations where ports have drafts suitable for floating substructure-turbine installation and can support the provision of O&M port services, distance to the wind farm is key which localises competition.

Vessel charter prices are a good example of the impact of pan-sector competition. Whether considering large floating vessels or common tugs, cyclic variations in regional wind and oil and gas activity can have a significant effect of price.

Supply chain evolution

Over time, the supply chain will mature, as it did in fixed offshore wind, with larger players taking on wider scopes and more risk. Wider scope within one supplier has enabled more cross-disciplinary collaboration to reduce cost. Also, larger volumes have facilitated investment in design, manufacturing and installation tooling suited to higher-volume process repetition. Large offshore wind farms may use 100 sets of identical (or similar) components, quite different from the more common practice in oil and gas of constructing one-offs.

Technology development

To date, the biggest driver over time of cost of energy reduction has been the development of new technology. The most visible sign of this has been the increase in turbine rating, increasing from 2 MW turbines 20 years ago to 15 MW turbines for projects reaching FID in 2028.

Larger turbines help drive down the per MW cost of floating substructures, installation and operation, whilst reaching higher into the wind field, so increasing energy production per MW installed. Larger turbines drive a need for technology development at a component level, as offshore wind turbines use the largest castings, bearings, generators and composite structures in series manufacture in any industry.

Technology development in floating substructure design and manufacture will have a major impact on LCOE. This cost element is specific to floating offshore wind and currently makes up a very large proportion of CAPEX. As the industry scales up and optimises floating substructures, significant cost reductions will happen, just as they have for cost components in fixed offshore wind. Innovations in foundation substructures, such as lighter, more optimised designs, will reduce the amount of steel and other materials needed, lowering material and fabrication costs. Integration between turbine and foundation design could also help reduce costs. As the industry scales up, economies of scale and streamlined supply chains will further drive down costs. Additionally, increased project experience, and improved installation technologies, will contribute to making floating offshore wind more affordable and commercially viable over time, although this is dependent on deployment rates.

Industry incorporation of digital, autonomous, artificial intelligence and other applicable technologies is also enabling significant cost reduction, especially through improved wind farm operation and control.

Time

Considering the supply chain and technical factors described above, LCOE is projected to reduce over time.

The chart below shows BVGA’s LCOE forecast for European floating offshore wind from 2027 (when the next pre-commercial floating offshore wind farms in the UK are expected to be commissioned) to 2035. We expect LCOE in the Asia Pacific region to follow a similar trend, although absolute values may change. LCOE varies between individual projects but overall LCOE is continuing to reduce significantly over time. The band shows the variance in LCOE that could occur for floating offshore wind projects driven by different site conditions, support mechanisms and local requirements that all impact LCOE. The variance is expected to tighten over time as the industry standardises across different technologies, and their associated manufacturing, installation and maintenance processes. The cost breakdown shown below reflects the higher commodity prices and altered market dynamics experienced by the industry post-2020. While some level of reduction in future commodity prices is expected, it is unclear on the timing or magnitude of this.

LCOE trend chart

While the LCOE of floating offshore wind is expected to decline significantly as the industry scales and technology matures, it is likely to remain higher than fixed-bottom offshore wind in most cases. Even as economies of scale and innovation reduce the LCOE for floating wind, the inherent technical challenges and material requirements will continue to make it more expensive than fixed-bottom projects. This is largely due to the added complexity of floating foundations, mooring systems, and dynamic cabling, as well as the need for specialised installation and maintenance strategies in deeper waters. Further, fixed and floating offshore wind have different deployment locations. Floating wind is designed to access deeper waters and more technically challenging sites that fixed-bottom technologies cannot reach. These locations often involve harsher metocean conditions, greater infrastructure demands, and more complex engineering requirements leading to higher costs.

Guide to a Floating Offshore Wind Farm